San Diego, CA | 2024 - Present

283 Design Build CMP) B-605 & 606 Repair 2 CDC Bldgs. RM 23-1148 (CBMM), Naval Base Coronado, CA

Project includes all design and construction work to renovate Child Development Center (CDC) Bldg. 605 and Bldg. 606 located at NASNI.  Primary focus of project is to refresh all areas within the Child Activity Rooms (CARs).  Roof work is also needed to sustain facility due to leaks causing classrooms to be taken out of service.  HVAC units are at the end of their usable life and must be replaced.


 

San Diego, CA | 2024 - Present

282 Design Build Demo Buildings in Poor Conditions and Misc. Improvements, NBPL, San Diego, CA

The project primarily consists of three components: demolition of existing buildings, minor modifications to existing buildings including new data drops and some other minor modifications, and replacement of existing generators.

Base Bid: Demolish building number 328 and provide associated site improvements and modify building number 320, 331, 332, and 346.

Option 01: Demolish building number 207, 528, Generator Shed, 558, and 581 and provide associated site improvements.

Option 02: B-309 & B-413 Generator Replacement.


 
 

Twentynine Palms, CA | 2024 - Present

281 Design Build TP21016M Repair Phelps Hall Dining Facility, Twentynine Palms, CA

Building 1460 is a 31,000 SF Dining Facility (DFAC) and is required to accommodate feeding Marines aboard the Installation.  With a seating capacity of 576 personnel, on a typical day, this facility is required to serve approximately 1728 meals, three times per day, 7 days a week. This project includes the Design and Construction of the mess hall and repairs all related management, supervision, quality control, labor, equipment, and materials to provide a complete and usable facility at Marine Corps Air Ground Combat Center (MCAGCC) Twentynine Palms, CA. In addition, the project will include repairs to the following priority areas: the entrance, dining area, circulation, galley, roofing and telecommunications for the B-146 Phelp DFAC.


 
 

Bremerton, WA | 2023 - Present

280 Design Build Remodel Second Floor & Add Passenger Cargo Elevator, B434, NBK Bremerton, WA

Building 434 is a 2-story and basement 21,708 square foot building consisting of a reinforced concrete structure. The basement level has exposed concrete exterior walls while the 1st and 2nd story have brick veneer over concrete. The project includes the remodeling of the entire 2nd floor in Building 434 in support of increased JCAB (JAG Consolidated Administrative Business) footprint. This area will primarily consist of administration work areas and offices.


 
 

San Diego, CA | 2023 - Present

279 Design Build NABSD-602 Renovate Bldg. RM18-1628 at SNI, Naval Base Coronado, CA

B602 is a three story 20,577 Unaccompanied Housing (UH) facility constructed in 1969 and located along the ocean front at the Silver Strand area of Naval Base Coronado.  The current B602 consists of 41 sleeping rooms (4-person rooms/164 beds) with a laundry room on each floor. The project will convert an existing Administrative Office into a sleeping room to increase the total to 42 (168 beds).  The existing building is in poor condition due to heavy wear and tear and exposure to the harsh marine environment and requires comprehensive renovation work to bring it up to current code and life safety standards. The building was last renovated in 2005 and most of the systems installed and remaining have passed their effective service life.  The complete renovation of B602 is intended to extend the service life of the building for 25 years while eliminating ongoing deterioration of the building structure from water infiltration.  The scope includes a new Elevator, Elevator Vestibules, Elevator Machine Room, and an Electrical Room designed to meet applicable codes and FC / UFC requirements.  This project also includes modifications at the Mechanical Room in B605 to replace the domestic hot water system including heaters, storage tank, controls, and accessories.